Subject: DEP Says MAJOR DEVELOPMENT GOOD, FARMING BAD on C1s
Sent: 21 Dec '06 16:32

 

Commissioner:

 

Unfortunately, Mr. Mauriello's interpretation of the buffer issue does not agree with REALsmart's previous understanding of this issue and the way it was originally framed at DEP.  In our understanding, the sole application of the "disturbance" clause as applied to C-1 buffer issues was to be the case in which agricultural uses would be continued and it would not apply under "change of use" zoning, such as the change from farming to major residential development.

 

Please note the following comments from REALsmart adviser, Bill Wolfe:

"Folks ­ the pragmatic answer to this is that the C1 buffer rules LEGALLY MANDATE that the developer PROVE, by a SCIENTIFICALLY VALID DEMONSTRATION, that the buffer reduction from 300 to 150 feet (and disturbance in the buffer between 150 and 300 feet) provides the EQUIVALENT protection of the functional values of 300 foot buffer

(under existing conditions) and maintains “existing water quality.”

 

Merely demonstrating what “existing water quality” is would take at least 4 quarters (one year’s worth) of water quality data collection. That delay alone would be sufficient to trigger any new HL regulations and the new stream encroachment rules.

 

Is there nothing living in the exiting buffer? No vegetation? No habitat? No recharge? No sediment and pollutant removal? No flood storage?  The Builder would have to show that these functional values of the buffer are retained by his development scheme such that the post-development condition is equivalent to the pre-development existing condition.

 

DEP could take years of technical review to reach these types of conclusions (e.g., issuing the builder a series of notices of deficiencies in proposed scopes of work for the various studies, et al).

 

If DEP wanted to do the right thing, it would be fairly easy." (end Mr Wolfe's comments)

 

Here it is @ NJAC 7:8-5.5(h)1.ii.

 

ii. Encroachment within the designated special water resource protection

area under (h)1i above shall only be allowed where previous development or

disturbance has occurred (for example, active agricultural use, parking area or

maintained lawn area).

The encroachment shall only be allowed where applicant demonstrates that the

Functional value and overall condition of the special water resource protection area

will be maintained to the maximum extent practicable. In no case shall the remaining

special water resource protection area be reduced to less than 150 feet as measured

perpendicular to the top of bank of the waterway or centerline of the waterway where the

bank is undefined. All encroachments proposed under this subparagraph shall be

subject to review and approval by the Department.

 

Link: http://www.nj.gov/dep/rules/adoptions/2004_0202_watershed.pdf

 

Commissioner, we hope that in view of the above, Mr. Mauriello's specious reasoning is debunked permanently, for it truly would make NJDEP a laughing stock. We continue to await the decision that you have promised in your email of October 17th, 2006, and please consider that approval of buffer reductions would:

 

1. Entirely contradict the policy thrust of Governor Corzine's Flood Mitigation Taskforce - recall that it had a distinct Delaware River focus. Use this link for information and materials: http://www.nj.gov/dep/njflood/

 

2. DEP approval would allow the Brandywine project to escape the restrictions of the

recently proposed new stream encroachment rules (the regulatory cornerstone of the Corzine Flood Mitigation Taskforce initiative).

 

 

Sincerely,

Mike King, Coordinator, REALsmart.